BNA Hilton Hotel
Time frame
2018-2024
Cost
$95 MILLION

Project Overview

As part of BNA Vision, Metropolitan Nashville Airport Authority (MNAA) pursed a public-private partnership to deliver a new terminal hotel and parking garage, expanding the airport’s amenities and supporting continued passenger growth. Paslay Group advised MNAA throughout the procurement, developer selection, negotiations, and financial evaluation process. The resulting development delivered a full-service terminal hotel and approximately 5,000 additional parking spaces, further strengthening BNA’s integrated airport experience.

Timeline:

2018-2024

Project Scope/Objectives:

  • Procure a private development partner for a new terminal hotel and parking facility
  • Establish a long-term P3 structure aligned with MNAA’s objectives and airport growth
  • Expand parking capacity and provide convenient, high-quality lodging directly at the terminal
  • Create a financially sustainable development that generates long-term value for MNAA
  • Deliver a full-service hotel with approximately 290 rooms, dining, meeting and event spaces fitness amenities and rooftop amenities

Approach:

Paslay Group supported MNAA from initial market engagement through financial close and developer selection. The team developed the RFI, RFQ, and RFP, evaluated market responses and financial proposals; facilitated seven collaborative dialogue sessions with prospective developers; and advised MNAA throughout negotiation. Paslay Group also worked with MNAA and the FAA to extend the concession term from 50 to 75 years, creating a stronger investment opportunity and supporting a competitive procurement.

Challenges/Obstacles:

The procurement required balancing airport objectives, developer investment requirements, FAA considerations, and long-term financial performance. The process also coincided with the onset of the COVID-19 pandemic, introducing significant uncertainty around future passenger demand and hotel performance. Paslay Group helped MNAA address these risks while maintain a competitive procurement and protecting the Authority’s long-term interests.

Implementation:

Following section of Chartwell as the developer, Paslay Group supported MNAA through negotiations and lease execution. The final structure incorporated mechanisms to address potential future changes in passenger demand while preserving the long-term economics of the agreement. The parking garage was completed in 2023, followed by the opening of the Hilton BNA Nashville Airport Terminal Hotel in March 2024.

Outcomes/Results:

The project delivered a new terminal-connected hotel and approximately 5,000 additional parking spaces, providing travelers with greater convenience and expanding BNA’s overall capacity and amenities. Through negotiations and financial analysis, Paslay Group secured additional value beyond the developer’s initial proposal and helped establish a long-term revenue structure for MNAA, including base rent, revenue participation, and potential future value from equity transfer or refinancing.

Lessons Learned:

Complex airport P3 procurements benefit from early market engagement, flexible transaction structures, and disciplined financial analysis. Maintaining competitive tension while addressing investor concerns can create greater value for the owner, particularly when market conditions change during the procurement process.